Emerson Network Power, Ponemon Institute Study finds significant increase in cost of unplanned data center outages since 2010

By Healthcare Facilities Today


Columbus, Ohio – Data center downtime proves to remain a costly line item for organizations, and the cost has increased significantly in the last three years, according to the results of the “2013 Cost of Data Center Outages,” a new Ponemon Institute study, sponsored by Emerson Network Power, a business of Emerson (NYSE: EMR) and a global leader in maximizing availability, capacity and efficiency of critical infrastructure. The study of U.S.-based data centers quantifies the cost of an unplanned data center outage at slightly more than $7,900 per minute. This is a 41 percent increase from the $5,600 it was in 2010, when Emerson Network Power first partnered with the Ponemon Institute to calculate the costs associated with data center downtime.

This year’s report analyzes costs at 67 data centers within the last year across varying industry segments with a minimum size of 2,500 square feet. It provides a comprehensive analysis of the direct, indirect and opportunity costs from data center outages, including damage to mission-critical data, impact of downtime on organizational productivity, damage to equipment, legal and regulatory repercussions, and lost confidence and trust among key stakeholders.

“Given the fact that today’s data centers support more critical, interdependent devices and IT systems than ever before, most would expect a rise in the cost of an unplanned data center outage compared to 2010. However, the 41 percent increase was higher than expected,” said Larry Ponemon, Ph.D., chairman and founder, the Ponemon Institute. “This increase in cost underscores the importance for organizations to make it a priority to minimize the risk of downtime that can potentially cost thousands of dollars per minute.”

Highlights of the 2013 Costs of Data Center Outages report include:

· Average cost of data center downtime across industries was approximately $7,900 per minute. (A 41 percent increase from the $5,600 in 2010.

· The average reported incident length was 86 minutes, resulting in average cost per incident of approximately $690,200. (In 2010 it was 97 minutes at approximately $505,500.)

· For a total data center outage, which had an average recovery time of 119 minutes, average costs were approximately $901,500. (In 2010, it was 134 minutes at about $680,700.)

· For a partial data center outage, which averaged 56 minutes in length, average costs were approximately $350,400. (In 2010, it was 59 minutes at approximately $258,000.) 

Those organizations with revenue models that depend on the data center’s ability to deliver IT and networking services to customers – such as telecommunications service providers and e-commerce companies – and those that deal with a large amount of secure data – such as defense contractors and financial institutions – continue to incur the most significant costs associated with downtime; with the highest cost of a single event more than $1.7 million.  

These same industries did see a slight decrease (two-to-five percent) compared to 2010 costs, while those organizations that traditionally have been less dependent on their data centers saw a significant increase. The largest increase was in the hospitality sector, which saw a 129 percent increase; followed by the public sector (116 percent), transportation (108 percent) and media organizations (104 percent).

“As data centers continue to evolve to support businesses and organizations that are becoming more social, mobile and cloud-based, there is an increasing need for a growing number of companies and organizations to make it a priority to minimize the risk of downtime and commit the necessary investment in infrastructure technology and resources,” said Peter Panfil, vice president, global power, Emerson Network Power. “This report gives these organizations the data they need to support more informed business decisions regarding the cost associated with eliminating vulnerabilities compared to the costs associated with not taking action.”

 Emerson Network Power also issued an infographic summarizing the costs of data center downtime and the findings of the study.

 In September, Emerson Network Power released the first part of this study, which surveyed more than 450 U.S.-based data center professionals and focused on the root causes and frequency of data center downtime. Survey respondents experienced an average of two complete data center outages during the past two years, while partial outages, or those limited to certain racks, occurred six times in the same timeframe. The average number of device-level outages, or those limited to individual servers was the highest at 11. These durations have declined slightly from 2010 findings (complete: 2.5, partial: 7, device level: 10).

Eighty-three percent of respondents said they knew the root cause of the unplanned outage. The top three most frequently cited root causes of outages remain unchanged from the 2010 report: UPS battery failure (55 percent), accidental EPO/human error (48 percent) and UPS capacity exceeded (46 percent). Thirty-four percent of respondents cited cyber attacks, which is up from 15 percent in 2010, while 30 percent cited weather-related reasons, which is up from 20 percent in 2010. Fifty-two percent believe all or most of the unplanned outages could have been prevented.

To download full details of the complete 2013 Ponemon Institute study and a podcast on the study, or to register for our upcoming webinar “The Increased Costs of Data Center Downtime and Best Practices to Prevent It,” visit www.EmersonNetworkPower.com/Downtime. For more information on technologies and services from Emerson Network Power, visit www.EmersonNetworkPower.com.

# # #

About Emerson Network Power

Emerson Network Power, a business of Emerson (NYSE: EMR), delivers software, hardware and services that maximize availability, capacity and efficiency for data centers, healthcare and industrial facilities. A trusted industry leader in smart infrastructure technologies, Emerson Network Power provides innovative data center infrastructure management solutions that bridge the gap between IT and facility management and deliver efficiency and uncompromised availability regardless of capacity demands.  Our solutions are supported globally by local Emerson Network Power service technicians. Learn more about Emerson Network Power products and services at www.EmersonNetworkPower.com.

 



December 4, 2013


Topic Area: Press Release


Recent Posts

Disinfectant Dispensers in Healthcare Facilities Often Fail to Deliver Safe Concentrations: Study

Study of 10 hospitals finds 90 percent have at least one dispenser delivering disinfectants at incorrect concentrations.


Duke University Health System Receives $50 Million for Proton Beam Therapy Center

The donation is the largest philanthropic gift received by Duke University Health System.


UT Southwestern Experiences Data Breach Through Calendar Tool

The incident occurred in October.


Protecting Patient Data: Strategies and Tactics

As cyber threats and breaches grow, healthcare organizations and facilities need a better approach to cybersecurity.


Duke Health to Acquire Lake Norman Regional Medical Center

The closing is projected for the first quarter of 2025.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.