Life Safety Q&A: Fire-rated door assemblies

Brad Keyes discusses fire-rated door assemblies

By Brad Keyes / Special to Healthcare Facilities Today


Q: You have stated in previous Q&As that all fire-rated door assemblies must be tested and inspected. I don’t think that is true on fire-rated door assemblies that are not located in a fire-rated barrier. I was under the impression that the hospital’s current Life Safety drawings would be the determining factor on what barriers the hospital was responsible for maintaining. For example, if the building had rated doors on a wall that was not denoted as a fire rated barrier on the LS drawings, one could justify why there were not maintained. I run into the installation of unnecessary rated doors in many facilities, both old and new.

A: You make an interesting case. However, the Life Safety Code always trumps everything else, and in this case it would trump the hospital’s LS drawings. According to 7.2.1.15.2 of the 2012 LSC, it clearly says all fire-rated door assemblies shall be inspected and tested in accordance with NFPA 80. There is no exception for fire-rated door assemblies that are not located in a fire-rated barrier.

My advice is to remove the fire-rated label if the facility is sure the barrier is not a fire-rated barrier.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 

 



September 13, 2017


Topic Area: Regulations, Codes & Standards


Recent Posts

Strategies to Eradicate Biofilm Containing C. Auris

Understanding the speed and risks of contamination after room disinfection should inform managers’ environmental cleaning recommendations.


Man Attacks Nurses, Police Officer at Jefferson Hospital

The man allegedly attacked the staff members before being restrained and sedated.


Freeman Health System Breaks Ground on New Full-Service Hospital

The construction project will be completed in three phases, over a 24- to 34-month time period.


All Eyes on Gen Z as They Enter the Workforce

As the labor gap widens in the facilities industry, not many managers trust Gen Z to fill that hole.


Cleveland Clinic Starts Fundraising Effort for New Hospital in West Palm Beach

Plans for the new hospital include approximately 150 inpatient beds, an emergency department, a medical office building and an ambulatory surgery center.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.