Regulations, Codes & Standards Q&A: Sprinkler obstructions

Brad Keyes discusses regulations for vertical clear space

By Brad Keyes / Special to Healthcare Facilities Today


Q: My question is in regard to NFPA 13 sprinkler obstruction compliance...We want to install some surveillance monitors in our security office along a wall. How much vertical clear space is required between the monitors to the ceiling, if the monitors will be 30 inches away, horizontally from the sprinkler head?

A: Those monitors may extend vertically up to the ceiling as long as they are not directly underneath a sprinkler head, and they are attached to the wall. You said they were 30 inches away horizontally from the sprinklers, so you should be okay.  

Section A.8.6.6 of NFPA 13-2010 says the following:

“The 18 in. (457 mm) dimension is not intended to limit the height of shelving on a wall or shelving against a wall in accordance with 8.6.6, 8.7.6, 8.8.6, and Section 8.9. Where shelving is installed on a wall and is not directly below sprinklers, the shelves, including storage thereon, can extend above the level of a plane located 18 in. (457 mm) below ceiling sprinkler deflectors. Shelving, and any storage thereon, directly below the sprinklers cannot extend above a plane located 18 in. (457 mm) below the ceiling sprinkler deflectors.”

While the monitor may not be shelves, the concept is the same.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 

 



October 10, 2018


Topic Area: Regulations, Codes & Standards


Recent Posts

Strategies to Eradicate Biofilm Containing C. Auris

Understanding the speed and risks of contamination after room disinfection should inform managers’ environmental cleaning recommendations.


Man Attacks Nurses, Police Officer at Jefferson Hospital

The man allegedly attacked the staff members before being restrained and sedated.


Freeman Health System Breaks Ground on New Full-Service Hospital

The construction project will be completed in three phases, over a 24- to 34-month time period.


All Eyes on Gen Z as They Enter the Workforce

As the labor gap widens in the facilities industry, not many managers trust Gen Z to fill that hole.


Cleveland Clinic Starts Fundraising Effort for New Hospital in West Palm Beach

Plans for the new hospital include approximately 150 inpatient beds, an emergency department, a medical office building and an ambulatory surgery center.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.