$1.5 billion Philadelphia healthcare pavilion project using lean practices, offsite fabrication

The project is using prefabrication for time-intensive construction like mechanical, plumbing and drywall work


The University of Pennsylvania's $1.5 billion medical pavilion project in Philadelphia is being managed with lean methods that rely on relationships, shared knowledge and common goals, according to an article on the Construction Dive website. 

The 1.5 million-square-foot Penn Medicine Pavilion will include 500 private rooms, an inpatient care unit for heart and vascular patients, neurology and neurosurgery units, a cancer center and an emergency department. 

The project is using prefabrication for time-intensive construction like mechanical, plumbing and drywall work. 

Five-hundred-and-fifty-nine mechanical racks, 504 bathroom pods and 47 zone valve boxes for medical gas are being constructed in a warehouse two miles away from the building site.

Read the article.



July 19, 2019


Topic Area: Project Management


Recent Posts

Dirty Floors: How Pathogens Can Accumulate and Spread Underfoot

Studies show that healthcare floors are covered in bacteria and can quickly spread throughout patient rooms. 


WellSpan Health Opens Its Newberry Hospital in Pennsylvania


Cahaba Center for Mental Health Ensnared in Data Breach

On March 28, 2025, Cahaba identified suspicious activity in an employee email account.


Reframing the Construction Manager as a Community Manager

Managers must work with patients, community residents and other interested parties to ensure a smooth, successful construction projects


Health First Celebrates 'Topping Off' Ceremony for New Cape Canaveral Hospital Campus

Construction is slated to finish by the end of 2026 or early 2027.


 
 