Aurora VA project getting another $100 million bailout

Construction will continue on a new veterans medical center near Denver


A project called the "biggest construction failure" in the history of the Department of Veterans Affairs -- already $1 billion over budget and more than a year behind schedule — is getting another $100 million taxpayer bailout, according to an article on the Everything Lubbock website.

Construction will continue on a new veterans medical center near Denver, expected to serve 400,000 former military service members and their families.

The $100 million funds three more weeks of work.

The costs to taxpayers for the project have already ballooned from an initial $328 million price tag in 2005 to $1.73 billion, with years more construction to go, according to government watchdog groups.

Read the article.

 

 



June 2, 2015


Topic Area: Industry News


Recent Posts

Contaminants Under Foot: A Closer Look at Patient Room Floors

So-called dust bunnies on hospital room floors contain dust particles that turn out to be the major source of the bacteria humans breathe.


Power Outages Largely Driven by Extreme Weather Events

Almost half of power outages in the United States were caused by extreme weather events.


Nemours Children's Health Opens New Moseley Foundation Institute Hospital


Code Compliance Isn't Enough for Healthcare Resilience

Intensifying climate risks are pushing hospitals to think beyond code requirements and toward long-term resilience.


Ribbon Cutting Marks First Phase Completion for New Montefiore Einstein Facility

The second phase is expected to be completed in the second half of 2027.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.