BIM/VDC made a complex MEP installation possible at Lurie Children's Hospital

Twenty-three stories up, the mechanical floor at the Lurie Children's Hospital in Chicago is a testament to the design and operations pressures the vertical strategy created.

By Healthcare Facilities Today


Built in a tight urban footprint, the Lurie Children's Hospital in Chicago had to go up instead of out. Rising 23 stories, the mechanical floor is a testament to the design and operations pressures such a vertical strategy created. The 12 layers of mechanical, electrical and plumbing (MEP) considerations in the 42-foot high space were made possible by a highly coordinated Building Information Modeling/Virtual Design and Construction (BIM/VDC) process, says an article in Building Design + Construction.

When the project to replace the nearby Children's Memorial Hospital began in 2005-06, using BIM and an integrated design process was far less common than it is now. And with non-repeating floor plans, the 1.25 million sq. ft., 288-bed hospital was a challenge by itself, to say nothing of the 60,000 sq. ft. 2-story mechanical floor.

By using a BIM/VDC process, the project team was able to detect clashes in systems and collaboratively resolve them in the model. "Tens of thousands of coordination issues were resolved virtually," says the article. From the 3D model, some subcontractors were able to prefabricate systems off site, improving accuracy and speed of installation.

The design team also made sure to heavily involve the operations and maintenance team, and so was able to build considerations for ease of operation into the design. For example, an access pathway safeguards access to equipment for maintenance and inspection. Due to the compressed footprint and layering of systems, however, some of the access routes are a bit tortured. One smoke damper called out in the article requires a trip up a ladder, across an air handler, getting through a 12-foot duct and then going up another ladder. 

The design team used laser scanners to create point cloud models of the MEP systems as they were installed, comparing the real-time installation to the BIM information. By doing this, necessary changes in the field were captured for the as-built drawings. 

Read the article.



May 20, 2013


Topic Area: Architecture


Recent Posts

Wider View: Planning LED Upgrades Across a Healthcare Portfolio

Upgrade planning has to start with a systemwide, portfolio approach rather than a site-by-site mindset.


Cone Health Plans Hospital in Forsyth County of North Carolina

The 198,593 square-foot facility will be in southeast Forsyth County.


Carvel Autism Health to Open New Therapy Clinic in Altoona, Iowa

The clinic features colorful, sensory-friendly spaces where children work one-on-one with therapists.


Cleanliness in Hospitals: Clinical Priority and Community Perception

EVS managers and communities value cleanliness for complementary reasons: managers for safety and compliance, communities for trust and comfort.


Dana-Farber Receives $50M Gift for Planned Cancer Hospital

A $50 million grant from the Yawkey Foundation will support construction of Dana-Farber Cancer Institute’s planned 450,000-square-foot cancer hospital.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.