BIM/VDC made a complex MEP installation possible at Lurie Children's Hospital

Twenty-three stories up, the mechanical floor at the Lurie Children's Hospital in Chicago is a testament to the design and operations pressures the vertical strategy created.

By Healthcare Facilities Today


Built in a tight urban footprint, the Lurie Children's Hospital in Chicago had to go up instead of out. Rising 23 stories, the mechanical floor is a testament to the design and operations pressures such a vertical strategy created. The 12 layers of mechanical, electrical and plumbing (MEP) considerations in the 42-foot high space were made possible by a highly coordinated Building Information Modeling/Virtual Design and Construction (BIM/VDC) process, says an article in Building Design + Construction.

When the project to replace the nearby Children's Memorial Hospital began in 2005-06, using BIM and an integrated design process was far less common than it is now. And with non-repeating floor plans, the 1.25 million sq. ft., 288-bed hospital was a challenge by itself, to say nothing of the 60,000 sq. ft. 2-story mechanical floor.

By using a BIM/VDC process, the project team was able to detect clashes in systems and collaboratively resolve them in the model. "Tens of thousands of coordination issues were resolved virtually," says the article. From the 3D model, some subcontractors were able to prefabricate systems off site, improving accuracy and speed of installation.

The design team also made sure to heavily involve the operations and maintenance team, and so was able to build considerations for ease of operation into the design. For example, an access pathway safeguards access to equipment for maintenance and inspection. Due to the compressed footprint and layering of systems, however, some of the access routes are a bit tortured. One smoke damper called out in the article requires a trip up a ladder, across an air handler, getting through a 12-foot duct and then going up another ladder. 

The design team used laser scanners to create point cloud models of the MEP systems as they were installed, comparing the real-time installation to the BIM information. By doing this, necessary changes in the field were captured for the as-built drawings. 

Read the article.



May 20, 2013


Topic Area: Architecture


Recent Posts

What Does Light Daily Cleaning Miss in Patient Rooms?

Most environmental services workers still clean as if they are wiping dust off a countertop, not disrupting a living, structured community.


Smart Lighting Overhaul Boosts Efficiency, Diagnostics and Wellness at Bryan Health

Case study: LED upgrade and advanced controls across Bryan Health campuses cut lighting energy use by 57 percent while enhancing patient care and staff productivity.


AdventHealth Opens New Freestanding ER in Florida

The approximately 13,700-square-foot emergency room features 12 patient rooms, respiratory therapy services, diagnostic imaging including CT scans, X-ray and ultrasound.


Dirty Floors: How Pathogens Can Accumulate and Spread Underfoot

Studies show that healthcare floors are covered in bacteria and can quickly spread throughout patient rooms. 


WellSpan Health Opens Its Newberry Hospital in Pennsylvania

This marks the opening of its 10th hospital in the region spanning Central Pennsylvania and Northern Maryland.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.