Case study

Catskill Regional Medical Center upgrades parking lot using green technology

Process eliminates the need to excavate, remove and dispose of failed pavement as well as the need to import large volumes of virgin aggregate


Like most aging pavements, the infrastructure at Catskill Regional Medical Center was past its useful life. The Harris N.Y. medical campus' roadways and parking lots were suffering. 

Along with a renovation of the hospital itself (currently underway), management prepared and entertained bids on both conventional pavement reconstruction and Full Depth Reclamation (FDR) with Cement as an alternate. 

Local paving contractor, Superior Surfacing Systems, Ltd. presented the facility two years prior with a proposed scope of work and budget for the process. Although unfamiliar with this method, the hospital and its consultant were interested in learning more about it.

The hospital selected T.M. DePuy Engineering to prepare bid documents for the conventional method of asphalt replacement. With input from Superior Surfacing Systems and the Road Recycling Council, a comprehensive alternate specification for the FDR with Cement process was prepared. 

Cost savings as a result of accepting the FDR with Cement solution were significant. So much in fact that the hospital was able to afford parking lot repairs in areas not originally budgeted for. 

The FDR with Cement process begins with pulverizing old/existing failed asphalt and blending with existing underlying subbase. Portland cement is incorporated into the material, placed, fine graded and compacted creating a fortified “reclaimed” product exhibiting a much higher strength and stability than conventional crushed stone base. 

The process eliminates the need to excavate, remove and dispose of failed pavement as well as the need to import large volumes of virgin aggregate. The cost savings on trucking, tipping fees and new stone base is significant as CRMC soon found out after reviewing the bids.

Although typically and historically used for municipal roadway projects, FDR with Cement proved to be a highly effective solution to the hospital’s ailing infrastructure issues and is rapidly gaining acceptance and popularity in the private sector.

Phase I of the project also entailed new concrete curb and sidewalk, new underdrain behind curb lines, topsoil, seeding and new pavement markings throughout the site. 

According to Jon Heimbach, Catskill Regional’s Construction Manager,

“The differences in the FDR with Cement process are very significant. Cost savings, reduction in on-site construction traffic, the ability to continue work in inclement weather, and the speed of reconstruction of our parking lots were all remarkable."

Subcontractor, Reclamation LLC of Kingston N.Y. performed the FDR with Cement process and shared grading responsibilities with Superior’s Project Superintendent Kevin Murphy.  “Having performed conventional site work throughout my career, I was a little apprehensive about the FDR process. I am very impressed with the results and the substantial benefits regarding the structural stability of the reclaimed subbase. Despite the challenging aspects of an active hospital site, the FDR with Cement process enabled us to move quickly through the project as evidenced by meeting our self-imposed deadline for completion to the exact day.” said Murphy.

For Superior, it was the first experience with FDR with Cement vs. conventional methods. The positive results and feedback from the customer have made converts of the company and they hope to pursue and complete additional projects of a similar scope as well as the planned Phase II portion of the hospital’s paving program.

 



April 16, 2015


Topic Area: Project News for Healthcare Facilities


Recent Posts

17 Million Patient Records Stolen in PIH Health Ransomware Attack

A ransomware attack halted operations across three of PIH’s hospitals.


Holidays are Prime Times for Healthcare Cyberattacks

A study found that 86 percent of organizations that experienced ransomware attacks were targeted on a holiday or weekend.


Hartford Healthcare Forms Partnership to Open Health Equity Clinic

The new clinic will open in January 2025.


UCHealth Reveals Plans for Memorial Hospital North Expansion

Construction on the patient tower is slated for 2026 with a projected opening to patients in 2029.


What Are 'Hospi-tels'?

Hospitals and hotels are partnering to better cater to patients and families.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.