RTA Architects/Smith Group JJR

Collaboration, immersion solve complex challenges at rehabilitation hospital

The planning process for Craig Hospital's $90 million expansion and renovation took a full year that began with a week of full immersion at Craig by the architectural team

By Healthcare Facilities Today


Craig Hospital’s $90 million expansion and renovation will set a new standard for collaboration in a complex health care environment, according to a blog by Stuart Coppedge of RTA Architects, on the Healthcare Construction + Operations website.

The 60-month project consists of approximately 85,000 square feet of new space, and approximately 135,000 square feet of existing space of renovation for the Englewood, Colo., hospital. The expansion will double the size of Craig’s outpatient clinic, including a new, state-of-the-art aquatic therapy pool and 52 new private rooms.

According to Coppedge, RTA, of Colorado Springs, Colo., serving as architect of record, partnered with design architect SmithGroupJJR and GE Johnson Construction to resolve a complex problem: How do you build a new facility on top of and inside an operating brain and spinal cord injury rehabilitation hospital without losing beds or disrupting patients?

The answer was to pull in experts from all disciplines and break the project into 22 pieces. The planning process took a full year that began with a week of full immersion at Craig by the architectural team, the blog said.

Seventeen months into the project, the architectural team as well as the contractors understand the Craig way, according to Coppedge

The architectural team found the immersion experience humbling, according to Randy Thorne, RTA’s principal in charge.

“When we pulled a nurse or therapist aside and asked what they needed in a new work space, we'd get a response like, ‘I've got plenty of room, I don't need a window,’ and that's a staff member working out of a five foot by seven foot closet. They’re always focused on helping the patient."

Read the blog.

 

 

 

 

 



December 3, 2013


Topic Area: Architecture


Recent Posts

Cleanliness in Hospitals: Clinical Priority and Community Perception

EVS managers and communities value cleanliness for complementary reasons: managers for safety and compliance, communities for trust and comfort.


Dana-Farber Receives $50M Gift for Planned Cancer Hospital

A $50 million grant from the Yawkey Foundation will support construction of Dana-Farber Cancer Institute’s planned 450,000-square-foot cancer hospital.


Clarinda Regional Health Center Reports Data Security Incident

On or around December 15, 2025, Clarinda learned that certain data within its network may have been accessed without authorization.


Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.