Life Safety Q&A: Four-inch corridor projection

Brad Keyes continues the discussion on regulations for med-room corridor doors

By Brad Keyes / Special to Healthcare Facilities Today


Q: With the adoption of the new 2012 Life Safety Code by CMS, we had a discussion about projections from the corridor wall. Since the LSC only allows projections to be 4 inches, the question that came up was in regards to fire extinguishers mounted to the wall and not recessed as they project out from the wall about 7 inches. Will we be required to recess them or will they be allowed? The same question was raised about wall mounted telephones?

A: Actually, the 2012 LSC allows a 6-inch projection into the corridor [see 19.2.3.4(4)], but CMS’ Final Rule published April 4, 2016 said they will enforce the more restrictive 4-inch maximum projection into the corridor, based on the Americans with Disabilities Act (ADA). For all healthcare facilities that receive Medicare & Medicaid funds, they must comply with CMS’ exception to the 2012 LSC.  

To answer your question, there are no exceptions to the 4-inch maximum projection rule. So, anything projecting more than 4 inches into the corridor, including fire extinguishers and telephones, would likely be cited by a surveyor or inspector. 

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 

 



August 2, 2017


Topic Area: Regulations, Codes & Standards


Recent Posts

Parking: Where the Outpatient Land Crunch Shows First

Healthcare systems that treat parking as a strategic design variable from the first feasibility pass will have more sites to choose from.


Clear Behavioral Health Opens New Outpatient Mental Health Center in Anaheim Hills

It offers an intensive outpatient program (IOP) for adults and teens ages 13 to 17 across east Anaheim and the surrounding communities.


Bon Secours Begins Construction on Freestanding Emergency Department in Norfolk

It is expected to open in late 2027.


The OR HVAC Puzzle: Why Individual Systems Are on the Rise

Extra penetrations, tight clearances and strict humidity needs—design experts explain what it really takes to plan dedicated units for each operating room.


Skanska Completes Renovation of Specialized Care Facility for Sutter Health

The project was delivered through a highly coordinated effort, utilizing advanced construction methodologies to maintain efficiency.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.