Focus: Disaster Preparedness

New plant to keep Mass. hospital running during disaster

Baystate Medical Center will be able to operate for 30 days if the power goes out


Baystate Medical Center in Springfield, Mass., will be able to operate for 30 days if the power goes out when a new power plant project is finished, according to an article on the WAMC website.

Baystate currently can operate its emergency room, neonatal intensive care unit, cardiac intervention center and other healthcare services critical to the region for four days if the power goes out in Springfield.

The new $27 million cogeneration plant will use a natural gas combustion turbine to generate electricity and the steam that comes as a byproduct is used to heat the hospital. The plant will provide the hospital with roughly 80 percent of its electricity usage.

The expected energy cost savings of close to $3 million annually comes at a time when Baystate has been tightening its belt.  More than 300 employees were laid off last month due to a round of budget cuts.

Read the article.

 



November 9, 2016


Topic Area: Sustainable Operations


Recent Posts

Every Detail Matters: A Patient's Story of Healing, Hope and Healthcare Facilities

In the Facilities in Focus season finale, 11-year-old Kendalynn and her mother share how Intermountain Primary Children’s Hospital became more than a place for care.


Geisinger Wyoming Valley Medical Center Tops Off New 11-Story Tower

The expansion will improve the patient experience by transitioning the hospital to all private patient rooms while significantly increasing clinical capacity.


PAM Health Announces Plans for Medical Rehabilitation Hospital in North Carolina

PAM Health Rehabilitation Hospital of Greensboro will be one of four new PAM Health inpatient rehabilitation hospitals currently planned in the state.


3 Ways to Minimize Disruption During Construction in Healthcare

Addressing potential construction challenges requires close collaboration among owners, facility managers, administrators, subcontractors and crews.


St. Luke's University Health Network to Open Heart Hospital in October

The new Heart Hospital adds 140 beds and nearly doubles the size of the Anderson Campus yet again.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.