Pandemic Prompts Major Changes in Middle of Construction

One change converted 12 intensive care rooms to feature slightly negative airflow

By By Dan Hounsell


COVID-19 changed so many things for healthcare facilities, from HVAC system operations to worker protection and even movement within buildings. For one healthcare system, the pandemic went so far as to prompt a major change of direction in the middle of a construction project.

When the University of Virginia (UVA) Medical Center began the design of its University Hospital Expansion, the plan called for expanding its emergency department (ED) and surgical suite and adding a six-story inpatient tower. 

By January 2020, the expanded ED and surgical floor were done. But the COVID-19 pandemic hit as the inpatient tower was months from completion, prompting UVA to make last-minute changes, according to Health Facilities Management

The hospital’s leadership met with architects at Perkins&Will to discuss accelerating its open date and redesigning the tower to accommodate more airborne infection isolation rooms.  

The first solution was to temporarily repurpose an existing smoke evacuation system to convert 12 intensive care rooms to feature a slightly negative flow. Combined with three existing airborne infection isolation rooms, the rooms gave the hospital 15 isolation rooms in less than two weeks.

The second solution provided the greatest number of beds for COVID-19 patients. Three 17-foot-high, high-velocity stack fans were installed on the roof to give additional patient rooms negative pressure.



March 11, 2021


Topic Area: Construction


Recent Posts

17 Million Patient Records Stolen in PIH Health Ransomware Attack

A ransomware attack halted operations across three of PIH’s hospitals.


Holidays are Prime Times for Healthcare Cyberattacks

A study found that 86 percent of organizations that experienced ransomware attacks were targeted on a holiday or weekend.


Hartford Healthcare Forms Partnership to Open Health Equity Clinic

The new clinic will open in January 2025.


UCHealth Reveals Plans for Memorial Hospital North Expansion

Construction on the patient tower is slated for 2026 with a projected opening to patients in 2029.


What Are 'Hospi-tels'?

Hospitals and hotels are partnering to better cater to patients and families.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.