Q&A: Fire-rated doors in non-fire-rated walls

Brad Keyes discusses requirements for a fire-rated doors in non-fire-rated walls

By Brad Keyes / Special to Healthcare Facilities Today


Q: If a fire door is in a wall that is not a fire-rated wall, will the wall need to be brought to be a fire-rated wall?

A: No… not typically. The location of fire-rated barriers (i.e. walls) are determined by the design professional (i.e. architect) when the facility is designed and constructed. Often times, after the facility is built and operating for a few years, new locations that require fire rated barriers are identified. These could include rooms that are newly designated as hazardous areas, or perhaps a building separation from a new addition.

It is not uncommon for some design professionals to specify fire-rated door assemblies in barriers that are not fire-rated. This may be due to a building code requirement, or it may be due to a misunderstanding of the codes and standards. For whatever reason, once these fire-rated door assemblies are installed, you must maintain them in accordance with NFPA 80 which includes annual fire-door testing and inspections. But there is no requirement to designate a barrier to be labeled as a fire-rated barrier simply because it has a fire-rated door assembly installed in it. To be sure where the fire-rated barriers are actually located, refer to the Life Safety drawings and/or original construction documents of the facility.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 



February 15, 2017


Topic Area: Regulations, Codes & Standards


Recent Posts

Alleged Ransomware Administrator Extradited from South Korea

The Phobos ransomware has been used globally to target over 1,000 organizations, including healthcare.


Design Plans Unveiled for New Intermountain St. Vincent Regional Hospital

The new hospital will be a 14-floor, 737,000 square-foot facility in Billings, Montana.


Ground Broken on New Pediatric Health Campus in Dallas

The new campus will replace the existing Children’s Medical Center Dallas.


Pre-Construction Strategies for Successful Facilities Projects

Savvy decisions can help facilities meet long-term goals by creating consistency and eliminating waste.


Geisinger Finds Success with Violence Prevention Efforts

Their safety measures included training staff in de-escalation, active-shooter response drills and equipping 6,000 employees with duress notification badges.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.