Regulations, Codes & Standards Q&A: Ceiling tile replacement

Brad Keyes discusses regulations for ceiling tile replacement

By Brad Keyes / Special to Healthcare Facilities Today


Q: I have several ceiling tiles (approximately 52) that are scratched or damaged that has sprinkler heads in them. Is there a code that references or mandates the replacement of the ceiling tiles? Also, I was told once the old/current sprinkler heads are removed to replace the ceiling tiles, new sprinkler heads have to be replaced. Is that true?

A: If the ceiling tiles are stained, most surveyors will have a problem with that as that implies water which can lead to mold or mildew. If they cite the stained ceiling tiles, it would be likely be cited under an Infection Control standard.  

If the ceiling tiles have gaps or cracks wider than 1/8-inch then that will likely be cited under a sprinkler installation standard or a smoke detector installation standard, as the ceiling needs to resist the passage of smoke in order for the smoke detectors and/or sprinkler to function properly. 

But a ceiling tile that is scratched is not a Life Safety Code deficiency and likely would not be cited. 

Yes… you cannot re-install used sprinklers (see section 6.2.1 of NFPA 13-2010), so if you need to remove the sprinkler head to change the ceiling tiles, then that is a great time to update to a newer style that uses escutcheons that are removable to allow easy replacement of ceiling tiles.   

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.



March 18, 2020


Topic Area: Regulations, Codes & Standards


Recent Posts

3 Employees Injured by Patient at Halifax Infirmary's Emergency Department

Police contained the threat and took the patient into custody.


How Architects Shape the Future of Healthcare Facilities

Healthcare architecture is more than just designing and building hospitals.


UNC Health, Duke Health Form Partnership for Stand-alone Children's Hospital

The partners plan to break ground together on the new NC Children’s campus by 2027.


Sarasota Memorial Hospital Plans to Build New Facility in North Port

The six-story, 100-bed hospital is slated to open in fall of 2028.


CMMS, Data and the Path to Compliance

Taking control of healthcare facilities data in CMMS enables managers to use it to ensure the efficient operation and maintenance of their assets.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.