Regulations, Codes & Standards Q&A: Corrective Maintenance Work

Brad Keyes discusses regulations on corrective maintenance work

By Brad Keyes / Special to Healthcare Facilities Today


Q: Thanks for all the great information that you provide; it is very helpful! I just have a quick question about corrective maintenance work orders. Do you know how many days a mechanic has to make repairs when the PM/equipment fails?

A: There are no set standards on how many days a technician may take to resolve a defective piece of equipment. In regards to a survey, CMS does have standards that say no more than 60- days are permitted to resolve deficiencies identified by a surveyor during a survey (an accreditation survey or a CMS validation survey), but that is not quite the same as a routine non- survey fix and repair situation. CMS also says if a particular LSC deficiency requires more than 60-days to resolve (i.e. time to design, competitive bidding, delivery lead-time, availability of space, etc.), then the organization may submit a Time-Limited Waiver request as part of their Plan of Correction to request more than 60-days to resolve an issue.

The expectation is the organization will take appropriate and immediate action to resolve all deficiencies, and when they cannot be resolved the same day they are discovered then an ILSM assessment must be conducted.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.



November 4, 2020


Topic Area: Regulations, Codes & Standards


Recent Posts

How Architects Shape the Future of Healthcare Facilities

Healthcare architecture is more than just designing and building hospitals.


UNC Health, Duke Health Form Partnership for Stand-alone Children's Hospital

The partners plan to break ground together on the new NC Children’s campus by 2027.


Sarasota Memorial Hospital Plans to Build New Facility in North Port

The six-story, 100-bed hospital is slated to open in fall of 2028.


CMMS, Data and the Path to Compliance

Taking control of healthcare facilities data in CMMS enables managers to use it to ensure the efficient operation and maintenance of their assets.


Healthcare is a Major Ransomware Target

Healthcare is the third-most-targeted sector, according to the report.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.