Special construction techniques are being used to construct California hospital parking structure

New 351-car parking structure will be primarily underground to ensure a clear view of the Henry Mayo Newhall Memorial Hospital from a major roadway

By Healthcare Facilities Today


The new four level design-build parking structure at Henry Mayo Newhall Memorial Hospital in Valencia, Calif., will be built with one level at grade and three levels underground in order to maintain an unobstructed view of the main hospital, according to a press release.

The elevator and ventilation shaft core at the corner of the structure will mimic the color palette of the adjacent medical office building creating a unified appearance. The structure was designed by Choate Parking Consultants.

“The new parking structure will provide much improved access to the front entrance of the hospital for our patients and visitors.  It will also support the additional parking needs of our soon-to-be-built inpatient bed expansion to meet the needs of our growing community,” said Roger Seaver, hospital president and CEO.

McCarthy Building Companies, Inc. is serving as design-build contractor and SHP Project Development is the construction manager for the 116,544-square-foot structure. With 351 parking stalls, the new parking facility is being built to serve the main hospital with secondary service to the new medical office building currently under construction.  

The project is scheduled to begin construction in March 2014 once the new medical office building is completed.

“Construction of subterranean parking structures always creates some interesting challenges,” said McCarthy reconstruction director Joseph Chung in the release.  “In order to build the underground parking facility, we will need to provide temporary shoring and lagging, as well as waterproofing on all sides of the perimeter retaining walls. To reduce costs, we were able to eliminate the shoring on one side by excavating a temporary slope along that particular side of the structure.”

Chung said the project requires substantial structural design coordination with the sequence of the cast-in-place concrete construction to minimize the post-tensioning forces (ie. “pull-in effect”) on the perimeter concrete retaining walls which will be connected to the superstructure.  

“An abundance of different options were evaluated to determine the best structural design solution,” said Chung in the release. “We spent a considerable amount of time collaborating with our structural engineers and coordinating our schedule with the construction sequence. We also needed to accommodate the necessary delays required to properly cure the walls in order to minimize the shrinkage.”

McCarthy plans to build this complex parking structure within an aggressive schedule of approximately eight months.

“To help ensure the project timeline and build it as efficiently as possible, we will use its own concrete crews experienced in using a pre-engineered Cunningham Deck and Beam Forming System to construct the structure,” said Chung.  

“The Deck and Beam structural design, which features long span, post-tensioned, cast-in-place concrete beams and decks, will allow us to re-use our formwork system from level to level, and we can construct the facility without the use of a crane and hoisting of materials. This process helps to maximize labor productivity and shortens the overall duration of the elevated deck pours.”

Chung said other project challenges include working on a live hospital campus while minimizing interruption to existing operations and keeping all access roads open throughout the project. 

“Our plan is to remain as invisible as possible while working on the hospital campus, just as we did when we built their first parking structure a few years back,” said Chung.

The parking structure is scheduled to complete construction by November 2014 and open a month later. 

 

 

 

 



October 21, 2013


Topic Area: Project News for Healthcare Facilities


Recent Posts

17 Million Patient Records Stolen in PIH Health Ransomware Attack

A ransomware attack halted operations across three of PIH’s hospitals.


Holidays are Prime Times for Healthcare Cyberattacks

A study found that 86 percent of organizations that experienced ransomware attacks were targeted on a holiday or weekend.


Hartford Healthcare Forms Partnership to Open Health Equity Clinic

The new clinic will open in January 2025.


UCHealth Reveals Plans for Memorial Hospital North Expansion

Construction on the patient tower is slated for 2026 with a projected opening to patients in 2029.


What Are 'Hospi-tels'?

Hospitals and hotels are partnering to better cater to patients and families.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.