Western Specialty Contractors Performs Complete Façade Restoration of Historic Catholic Church


While many churches across the United States are closed during the COVID-19 pandemic, one Catholic parish in Union, Missouri used its closure to make much-needed repairs to its historic church.

St. Joseph Neier Catholic Church hired Western Specialty Contractors – St. Louis Masonry branch at the end of March 2020 to perform a complete masonry restoration on its 9,000-square-foot church’s façade. The historic church was originally constructed in 1868. In 1897, the upper part of the tower and the 90-foot steeple were completed. Renovations were made to the church in 1961, then again in 1998.

Roughly 25 percent of the façade’s masonry had been skimmed previously, meaning the mortar had not been properly removed before new mortar was installed over it. The façade’s remaining, original mortar was cracking which was allowing moisture into the walls. The façade was also stained with atmospheric and biological growth.

Western’s crew of five workers tuckpointed 100 percent of the façade’s brick joints using a more breathable type of mortar (Type O) than the original, which was likely constructed from materials dug up from the surrounding riverbanks.

“A Type O mortar was used because it has a higher lime content than other types of mortar, which makes it softer and more permeable,” said Brandon Lange, St. Louis Masonry Branch Sales/Project Manager. “This type of mortar accommodates movement. The existing brick is very soft. Using a hard mortar could lead to the soft bricks cracking.”

Western also replaced any missing bricks and all sealants at the window/door perimeters. Workers completed the project by cleaning the entire façade and applying a water-repellent. The project is expected to be completed in May 2020 within budget.

For more information about Western’s historic façade restoration expertise, visit the Western Specialty Contractors branch location nearest you - http://www.westernspecialtycontractors.com/western-locations/.



May 21, 2020


Topic Area: Press Release


Recent Posts

Waco Family Medicine Achieves Savings and Bold Design with Wood Selections

Case study: The healthcare facility incorporated over 25,000 square feet of wood and saved over $400,000.


Alleged Ransomware Administrator Extradited from South Korea

The Phobos ransomware has been used globally to target over 1,000 organizations, including healthcare.


Design Plans Unveiled for New Intermountain St. Vincent Regional Hospital

The new hospital will be a 14-floor, 737,000 square-foot facility in Billings, Montana.


Ground Broken on New Pediatric Health Campus in Dallas

The new campus will replace the existing Children’s Medical Center Dallas.


Pre-Construction Strategies for Successful Facilities Projects

Savvy decisions can help facilities meet long-term goals by creating consistency and eliminating waste.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.